DMS 4.2 EN 07/2011 TD17 L 91
Control technology | CANopen communication manual
Defining the minimum cycle time of the PLC project
Optimising the system
12.4 Optimising the system
How to optimise the system:
1. Log in and load project.
2. Check the task processing times.
3. Optimising cycle times:
• If required technologically, the cycle times of the remaining tasks with lower
priorities can be decreased.
• Condition: No task with a low priority may assign more than 60 percent of the
corresponding cycle time in its task utilisation.